RC meeting and Run Plan, Wednesday February 8th

From SBS wiki
Jump to: navigation, search

Return to the RC Meeting Calendar


RC Report


Current Status

  • Waiting to do full beam checkout when machine is ready.

Run Plan

  • When ops are ready to send us beam. Do full beam checkout and then continue production running on polHe3, hopefully 45uA.


Requested Accesses to the Hall

  • Time of next access opportunity currently not clear
  • GEM team need like a 3-4hour access for the SBS GEMs DAQ troubleshooting

Notices for Shift Crew

  • Check the How To page
  • Pay attention to the beam restoration procedures in the How To
    • there is a procedure if beam has been away for 30minutes, and another procedure if machine has been down for tuning or something which may change beam profile. Communicate with MCC to figure out why beam has been down and to figure out which kind of restoration you should do.
  • SL:
    • production runs (1-1.5hr) and replays (50k replay for each run, ~two runs also with 200k replays per shift if possible)
  • TOs:
  • Contact RC any time for any questions


Useful Links