RC meeting and Run Plan, Wednesday Oct. 11, 2023
From SBS wiki
Return to the RC Meeting Calendar
RC Meeting Information
Time: Monday - Friday at 3:30pm
- Location: Counting house conference room
- ZoomGov Meeting Connection Information
https://sbs.jlab.org/cgi-bin/DocDB/private/ShowDocument?docid=431
Useful Links
Procedures
Hall A call-in instructions:
- Call RC first.
- Techs on site 7am-4:30pm Mon-Thu, 7-11am Fri. RC will call Hall A work coordinator (Zach) during normal working hours. After hours, RC calls Tech on-call.
- After 9pm everything non-emergency needs to be deferred. What is emergency and what's not? Call RC. RC talks with Mark to decide.
Hall Access procedure:
- Access check list (binder on the counting room desk) needs to be filled out before making an access.
- Scan (take pictures with phone) and post it to the logbook.
- Any work inside the SBS, BB boundary need to have PS locked out -- requires two QEWs to throw the big switch. Exception: field measurements.
New instruction for shift crew when changing target:
- Beam restoration instructions have been updated. Printed version is in the counting room.
- When we change target, make sure the SOFs of Target BPMs are set to the correct values.
- SOFs for different targets: Needs an update after restoring beam tonight (Note: SOFs for major target positions are on the Control Room whiteboard.)
Status Update
Overall Summary
Day Shift Plan
- Taget spun up overnight at OFF/OFF magnet configuration
- NMRs taken every 3 hours.
- Lasers off and locked out at 9am by Todd and Arun.
- Beginning of alignment work in the hall
Swing Shift Plan
- Plan to be done and locked up by 5pm to restore hall to power/beam permit.
- Spin up for a few hours
- Hunter perform EPR calibrations around 8/9pm.
Beam After Maintainance
- MCC Expect to be able to start delivering beam back to halls about 8pm. (Naturally, anticipate this being slightly later, thus giving us EPR time).
- Hopefully, complete beam recovery and checkout in the remainder of Swing Shift / Early Owl shift, and proceed to take production data on the new cell.
Opportunistically between spin ups (?):
- H2 Reference data
- Single foil optics data
- Moller measurement
Accelerator status
- Beam stopped to halls 7am and North Linac opened.
- Maintenance day and beam studies during Day shift today (Wednesday 10/11)
- Beam expected back around 8pm.
- If you want to get into the hall, please communicate with the RC to get this organized!
Data collected :
N/A
Hall A Subsystems Status
Target
- Ladder Alignment in progress
Detectors
- All HV currently off. Hall is in controlled access.
- BBCal 7.4 dead. Discussion on changing PMT base at next available time.
Magnets
- SBS and BB are off. Hall is in controlled access.
Hall access requests
If anyone wants to make an access, let the RC know!
Shift schedule
IMMINENT OPEN SHIFTS
- Thursday 10/12 OWL (Target Operator)
- Friday 10/13 OWL (Target Operator)
- Saturday 10/14 DAY (Target Operator)
Please check when your shifts are!
https://misportal.jlab.org/mis/physics/shiftSchedule/?experimentRunId=SBS-GEn-2022
Please sign up for any open shifts!
Running Plan
- Standard production running at 45uA, with NMRs every 3 hours.
==> List of items in case He3 production running isn’t ready:
- Take data on reference cell at 10 atm H2 (portions that add up to 1 day) [85% (4200 elastic events) more data required for Bigbite momentum calibration]
- BigBite Sieve slit => only during day (Techs needed)
- with 8 carbon foils and take optics for 1 hr at 40 uA (Sean/Andrew - confirm time)
- 1 hour for single foil (magnets off) => Chance BBcal HV setting to appropriate values
- BigBite/single foil location reconstruction (~20 mins?) - BigBite + HCAL detector experts on call consulting analysis experts like Andrew/Sean (magnet on)