RC meeting and Run Plan, Monday November 22th
From SBS wiki
Revision as of 20:11, 22 November 2021 by Brads (Talk | contribs) (→Run Plan for When Beam Returns (Tuesday Evening or Wednesday))
RC Meeting Information
RC Daily Meetings are at 3:15pm, remote connection link: https://bluejeans.com/256205934
Current RC: Brad Sawatzky
Accelerator and Hall Status
- Hall A is in Restricted Access and the configuration change to SBS-11 is underway -- will continue through Tuesday DAY shift
- We need to ensure that HVs are off when the Techs are working. They can be turned on for tests during SWING/OWL (check with the RC and make clear Halog entries please!)
- Downstream beamline bled up -- holding well
- Hall A Technical staff has priority during changeover
- GEM and Grinch experts plan to continue opportunistic debugging while we're down.
- 4th pass separator repairs are ongoing
- PD Update: 4th Pass IOT
- This primarily impacts Hall C at this point, but there will be downtimes associated with reintegration and tuning once repairs are completed.
- Heat off in the Hall A Gas Shed - back on (This can cause incorrect readings from the BGA.)
Plans for the next few days
- The pass change has tentatively been moved to Tuesday Swing/OWL (instead of Wed Day) -- assumes reasonable Accelerator uptime Mon/Tuesday
- Final confirmation of pass change date will be Tuesday morning RC meeting, but we will proceed under the assumption that pass change will occur Tuesday SWING/OWL.
- Shift Leaders have been notified that their shifts are cancelled through Tuesday OWL shift.
- Tuesday DAY shift personnel should come in as planned. The Tuesday DAY shift leader is free to arrive at noon if he would prefer.
Additional details in sub-section notes below.
Run Plan for When Beam Returns (Tuesday Evening or Wednesday)
The SBS-11 Runplan (PDF) document is on the DocDB. Please update the file there if needed. This runplan is a draft. Stay tuned for changes (and updates to the ??? below.)
- Take BBCal cosmics data with magnets on to get HV settings established as soon as Hall can be locked up
- Beam restoration to the Hall
- Start with Sieve IN
- Ensure target is OUT
- GEM HVs OFF
- SBS, BB OFF
- All other systems should be ready to go
- After initial steer-up into Hall is complete
- Verify beam profile with Harp scans
- Ramp BB and SBS to production currents
- Determine raster size and position on target
CONFIRM: Production SBS current is 2100A (100%) or 1785A (85%)?
- Initial threshold settings for BBCAL and HCAL
- [FIXME] BBCAL threshold 0.5 GeV (??? mV)
- [FIXME] HCAL threshold ??? (??? mV)
- Turn GEM HV back ON; Ensure other detectors are ready to go.
- Optics Runs for SBS-11
- Zero Field Alignment
- SBS OFF, BB OFF, Sieve IN
- single C foil target
- [FIXME] BBCAL threshold 0.5 GeV (??? mV)
- I = 5--10 uA
- 60 min of beam on target
- Vertex and Angle Reconstruction 1/2
- SBS ON (1785A pos.), BB ON (750A neg.), Sieve IN
- 5-foil Optics target
- [FIXME] BBCAL threshold 0.8 GeV (??? mV)
- I <= 20 uA
- 60 min of beam on target
- Vertex and Angle Reconstruction 2/2
- SBS ON (1785A pos.), BB ON (750A neg.), Sieve IN
- 4-foil Optics target
- [FIXME] BBCAL threshold 0.8 GeV (??? mV)
- I <= 20 uA
- 60 min of beam on target
- Escorted Access to take Sieve OUT (needs trained personnel!)
- Low current GEM runs
- SBS ON (1785A pos.), BB ON (750A neg.)
- [FIXME] BBCAL threshold 2.0 GeV (??? mV)
- 1 uA on LH2 target
- Take ____ 5 min long runs with different GEM HV settings for quick voltage scan
- [FIXME] GEM HV Settings TBD for efficiency scan
- GEM Rate Study
- Ensure GEM HVs are back at standard settings
- SBS ON (1785A pos.), BB ON (750A neg.)
- [FIXME] BBCAL threshold 2.0 GeV (??? mV)
- LH2 target
- I=1 uA ; take 1 30min run
- I=15 uA ; take 1 30min run
- I=5 uA ; take 1 30min run
- I=1 uA ; take 1 30min run
- Move to Production Running cycle
- SBS ON (1785A pos.), BB ON (750A neg.)
- [FIXME] BBCAL threshold 2.0 GeV (??? mV)
- [FIXME] HCAL threshold ??? (??? mV)
- Goal: HCAL calib
- LH2 Target; I = 15uA
- 10M triggers (nom. 1 hr)
- Goal: Production
- LD2 Target; I = 8uA
- 40M triggers (nom. 4 hr)
- Goal: HCAL calib
- LH2 Target; I = 15uA
- 10M triggers (nom. 1 hr)
- Goal: Production
- LD2 Target; I = 8uA
- 30M triggers (nom. 3 hr)
- Goal: Production/Dummy
- Dummy Target; I = 15uA
- 2.5M triggers (nom. 0.5 hr)
- This nominally takes us to Friday 11/26 in the SBS-11 Runplan (PDF) document. Progress will be reassessed and subsequent runplan updated as needed.
- Upcoming shift schedule issues https://misportal.jlab.org/mis/physics/shiftSchedule/?experimentRunId=GMn-2021
- Several open TO positions starting Nov 26 (Bill H. picked up shifts on 24,25)
- John Arrington's Tuesday Swing shift is marked 'Trade Requested', but he's been confirmed.
- Shift Leaders have been notified that their shifts are cancelled through Tuesday OWL shift (during config change)
- Tuesday DAY shift personnel should come in as planned. The Tuesday DAY shift leader is free to arrive at noon if he would prefer.
Reminders / Notes
- Role sharing between SL and TO was discussed
- TO should support the SL wherever possible while still keeping primary focus on the target
- Beam Time accounting; Shift Checklist tasks are low-hanging fruit
- Suggestion is to have TO start/stop runs and maintain the Run Log spreadsheet?
- TO should support the SL wherever possible while still keeping primary focus on the target
- Run plan communication / documentation will be 'officially' documented on the Daily_Meetings#RC_Meetings page
- Don has made the Run Coordinator 'Run Plan / Report' page more visible on the wiki (and nicely formatted it)
Subsystem Updates
- HCal:
- HCAL timing plots are being updated/corrected
- Wiki instructions have been updated
- Working on clustering in SBS offline
- Will be using old HVs for SBS-11 startup
- BBCal:
- New HV settings made for upcoming BB/SBS on/off settings
- Contact BBCal experts to load these and monitor BBCal performance during beam restart
- New HV settings made for upcoming BB/SBS on/off settings
- Timing hodoscope:
- working on RF alignment
- HV instructions for hodoscope are in the wiki (and also re-posted to halog)
- Grinch:
- Study of LED data taken under different BB+SBS conditions underway
- Maria/Todd/Bradley will be taking some more opportunistic LED pulser data tonight (Monday)
- Status update to Halog was requested
- GEMS:
- GEM experts will be monitoring the gas bottles over the holidays (should be fine, but extra eyes will help)
- GEM HV Cosmic Scan Status
- No analysis of these runs yet(?)
- Likely still a good idea to do a (quick) 'voltage scan' with beam as well. Details TBD
- This will be a GEM-expert driven program.
- Work continues on calibrating/understanding the new GEM layer
- Andrew reports things seem to be generally working, but some issues still being worked on
- Identified an incorrect guess/assumption for the z-location. When corrected, that significantly improved tracking performance (the steep incident angle for cosmics makes tracking particularly sensitive to the z-location of the layers)
- Still investigating the following: large number of fake tracks; possible issues with pedestal suppression, or perhaps indication of cross-talk; unclear...
- GEM "HV-off" cosmics data are on disk -- not clear if it has been looked at (may help disentangle potential cross talk sources)
- Some confusion over an apparent latency shift for the new UV layer?
- Source of shift is not understood
- New data taken with a shifted latency in DAQ configuration, but still to be looked at
- Some confusion over a large latency shift occurred after the 2 APVs in the UV layer were fixed
- Run 12131 (Friday 1pm) shows this shift, old timing was present in run 12101 (Thursday morning). May have shifted around the time of the pedestal run?
- Alex, Andrew, and other DAQ/GEM experts will try to nail down the timing and cause of this shift
- Beamline:
- Clock signal rates measured here: https://logbooks.jlab.org/entry/3946822 [Resolved]
- L-HRS scaler gate fixes and notes: [1], [2] (Bob. M)
- Notes that the ET events have not been checked recently
- David F is looking at scaler sanity checks with Paul
- DAQ:
- CODA ET library updated Monday afternoon
- Alex will do some stress tests on DAQ while the Hall is open
- General DAQ stability?
- Frequent crashes at start or end of run
- New runs frequently do not start successfully and require cycles of reset/config/reset
- Could be ET issue, but some failures tied to VTP crate as well
- CODA ET library updated Monday afternoon
- Replay analysis:
- GEM work is ongoing (see above)
- Eric working on end-of-run report file output along with Dave F.
- Updates to BCM Scaler Database Files (David F.)
- Fixes some duplicate variable names in the TSsbs tree
- Counting House Computer requests [Ole will be looking into a number of these items]
- analyzer updated on hadesk machines
- Streamline access to common tools (halog, go_* scripts, etc)
- Perhaps get them in a common bin/ directory and added to $PATH?
- Firefox configurations differ quite a bit depending on user@host
- Update common configuration to improve useful bookmark toolbar links
- halog, elog, SBS wiki, Shift crew help, etc
- 'New' tabs default to something useful, etc