RC meeting and Run Plan, Friday September 23rd

From SBS wiki
Revision as of 13:54, 26 September 2022 by Jonesdc (Talk | contribs) (Commissioning run plans)

Jump to: navigation, search

Daily_Meetings

RC Meeting Information

Run Coordinator: Donald Jones

Location: Counting House Conference Room

Time: 3:00PM


Commissioning run plans

  • Beam line (1-2 shifts) Sept 30.
    • Beam centering and target alignment
    • Raster calibration
    • BCM and BPM calibration
  • Corrector adjustment procedure
  • GEMs run plan
  • Charge feedback system
  • Optics and calibration
  • Moller polarimeter (1 shift) Oct 7
  • Target commissioning
  • Bigbite commissioning (preshower, shower, GRINCH)
  • HCal commissioning

Subsystem status reports

  • Hall A Status -- Jesse Butler
  • Target status/timeline (training?) -- Arun
  • Beam line:
    • Monitors (calibration) -- Simona
    • Correctors -- Bogdan, Iuliia
  • Tentative run plan document -- Bogdan
  • Alarms
  • Analyzer -- Andrew
  • DAQ -- Alex
  • HCal -- Jiwan
  • Spectrometer magnets -- Jack
  • GEMs/Tracking -- Holly
    • Are new HV controls, alarms, gas flow monitoring procedures, EPCIS tracking in place?
    • Shift checklist ok?
  • Shower Calorimeter -- Provakar
  • Beam polarization -- Don

Minutes

We had a short meeting. Jack reported that the SBS magnet tripped at 90% and likely required replacement SRCs. This might take a while since he doesn't have any onsite. Alex says the DAQ is working. Holly says the alarm handler is working but folks should let her know if more things need to be added. Simona is continuing to perfect the run plan for bringing beam safely and establishing the raster. The laser system has not received its final inspection and approval. Likely Monday. Jack will continue testing the magnets. When he is done, Todd and co. will continue preparing the target ladder. Tuesday we are expecting to have survey of the target.