RC meeting and Run Plan, Monday December 12th
From SBS wiki
Return to the RC Meeting Calendar
Contents
RC Meeting Information
Current RC: | Eric King [ericking (@jlab.org or @temple.edu)] | |
Time: | Daily at 3:30PM | |
Location: | Counting House Conference Room |
Remote Connection Details
- Join ZoomGov Meeting
- https://jlab-org.zoomgov.com/j/1619032184?pwd=aWhTVWxya1ZZQzA1K2ZPSTd2ZX...
- Meeting ID: 161 903 2184
- Passcode: 260715
- Dial by your location
- +1 669 254 5252 US (San Jose)
- +1 646 828 7666 US (New York)
- +1 551 285 1373 US
- +1 669 216 1590 US (San Jose)
- 833 568 8864 US Toll-free
- Find your local number: https://jlab-org.zoomgov.com/u/acj3pTicMx
Shift Schedule
Until Shutdown
All shifts are full! :)
Accelerator Status
- Accelerator was down at the end of SWING for 45 minutes. [DT Event ID: 17472]
- Hall C valve/vacuum repair is complete; they're coming back online Tuesday; they will be priority hall next week.
Current Status
Taking production data on 3-He
Shift Summaries
Things That Happened
- HH Hodoscope voltages dropped on Sunday OWL (IDK, if this is wholly unusual). [4099867]
- Scalar helicity histogram from run 3191 50K Replay showed all zeros. [4099876]
- This was about 30 minutes of lost data.
- I only found one HALOG post while talking to SL, advised SL to start new run when accelerator returned beam and verify helicity data correct.
- SL should make reviewing 50K plots high priority.
Beam Current
We've been happily running at 40uA.
- (Saturday) I asked Sebastian to make a record of the ramp rates over the course of the past 8 hours during Saturday SWING and he went an extra step. [4099752]
- (Sunday) Bill has taken this further and created a strip chart that tracks this continually that seems to work very nicely. [4099956}
Target
Target polarization has been stable. List of the recent polarizations
- SUN 08:34 → 40.3% [4100316]
- MON 04:34 → 40.9% [4100229]
- MON 00:41 → 41.0% [4100152]
- SUN 20:38 → 40.8% [4100093]
- SUN 17:31 → 41.3% [4100050]
- SUN 14:04 → 41.6% [4099992]
Target Operator issues:
- (Sunday) Bill noticed that the wrong laser software was running on polhe1; he corrected the issue. [4100010]
- Junhao has complained that the Windows target VNC screen keeps locking, this is a nuisance. [4100065]
Issues Resolved
- Bill Henry has resolved the communication issue regarding the Moller HH magnet. Thank you, Bill. [4099942]
- Bill spoke with Zeke about GEM RED alarm panel items about this and they agreed to bring the topic up in Monday's RC Meeting.
Issues remaining
- BB GEM APV unreachable and cannot be repaired at this time.
Short Term Run Plan
- Continue production run on He3 target, 40 uA
- Use GEnII-noSBSGEMs DAQ config
- Use ps3=0, ps5=6, others =-1
- BBCal threshold at -366 mV, HCal threshold at -19 mV
- NMR measurement every 3 - 4 hours, close to 4 hours is better
Planned Accesses to the Hall
None
Special Requests
Please email me ericking (@jlab.org or @temple.edu) if there's something to be added.
Notices in Effect for Shift Crew
- Power down SBS, BB, and Detector HV before making an access to the Hall
Data Collection Status
- 77 out of 141 days (~54.6%)
- (NEEDS TO BE UPDATED) Total uncorrected accumulated charge on He3: 53.937 C out of 232C (23.25%)
- 2-Pass: 13.467 C
- 3-Pass: 40.470 C (@ end of SUNDAY DAY)