RC meeting and Run Plan, Friday September 30th
From SBS wiki
RC Meeting Information
Run Coordinator: Donald Jones
Location: Counting House Conference Room
Time: 3:00PM
Main topics for discussion
- Target cell work (alignment and installation update)
- Laser work
- Magnet tests
- Shift schedule (target operator training/shifts)
- Limited RADCON support over weekend (Doug H.)
Commissioning run plans
- Beam line (1-2 shifts) Sept 30.
- Beam centering and target alignment
- Raster calibration
- BCM and BPM calibration
- Corrector adjustment procedure
- GEMs run plan
- Charge feedback system
- Optics and calibration
- Moller polarimeter (1 shift) Oct 7
- Target commissioning
- Bigbite commissioning (preshower, shower, GRINCH)
- HCal commissioning
Subsystem status reports
- Hall A Status -- Jessie Butler
- Target status/timeline (training?) -- Arun
- Beam line:
- Monitors (calibration) -- Simona
- Correctors -- Bogdan, Iuliia
- Wiki, shift schedule, shift checklist -- Don
- Tentative run plan document -- Bogdan
- Alarms
- Analyzer -- Andrew
- DAQ -- Alex
- HCal -- Jiwan
- Spectrometer magnets -- Jack
- GEMs/Tracking -- Holly
- Are new HV controls, alarms, gas flow monitoring procedures, EPCIS tracking in place?
- Shift checklist ok?
- Shower Calorimeter -- Provakar
- Beam polarization -- Don
Minutes
Still trying for beam on Monday morning. This requires completing laser power tests and magnetic field measurements. These will be completed tonight and during the weekend in preparation for Jessie and crew to start hot checkout during Owl Monday. Discussed run plan for first few days.