GEN-RP KLL run plans

From SBS wiki
Jump to: navigation, search

<< SBS Main

Daily run plans

Daily run plans are now included in the Daily RC Meetings


Run plan summary

The plan is to run for 23 days with 2-pass beam before switching to 3-pass beam for KLL production data-taking (for 5 days). The plan includes the following steps:

  1. Establish beam in the hall and center on target
  2. Detector and DAQ check-out
  3. Optics commissioning
    1. BB GEM-hall alignment
    2. BB optics runs
    3. SBS GEM-hall alignment
  4. Calibration data without steel analyzer
    1. SBS 70% on LH2 and LD2
    2. SBS 100% on LH2 and LD2
  5. Calibration data with steel analyzer
    1. SBS GEM-hall alignment?
    2. Elastic calibration on LH2
  6. GEn_RP Production running on LD2
    1. SBS 100%
    2. SBS 70%
    3. SBS 100% contd
  7. KLL commissioning (analyzing power calibration)
  8. KLL production running

Steps 1 - 4 should be taken before the steel analyzer is inserted.

We want to take two Moeller measurements during the 2-pass run period. This will depend on running conditions and the availability of Don and team.

Detailed run plans

GEn-RP/K_LL 2-pass run plan

Program plans