GEN-RP KLL run plans
From SBS wiki
<< SBS Main
Daily run plans
Daily run plans are now included in the Daily RC Meetings
Run plan summary
The plan is to run for 23 days with 2-pass beam before switching to 3-pass beam for KLL production data-taking (for 5 days). The plan includes the following steps:
- Establish beam in the hall and center on target
- Detector and DAQ check-out
- Optics commissioning
- BB GEM-hall alignment
- BB optics runs
- SBS GEM-hall alignment
- Calibration data without steel analyzer
- SBS 70% on LH2 and LD2
- SBS 100% on LH2 and LD2
- Calibration data with steel analyzer
- SBS GEM-hall alignment?
- Elastic calibration on LH2
- GEn_RP Production running on LD2
- SBS 100%
- SBS 70%
- SBS 100% contd
- KLL commissioning (analyzing power calibration)
- KLL production running
Steps 1 - 4 should be taken before the steel analyzer is inserted.
We want to take two Moeller measurements during the 2-pass run period. This will depend on running conditions and the availability of Don and team.
Detailed run plans
Program plans