RC meeting and Run Plan, Thursday February 23th
From SBS wiki
Contents
RC Report
- https://logbooks.jlab.org/entry/4137361
- RC: Zeke Wertz ewertz@wm.edu
Summary
- Beam Delivery until middle of Owl was reasonable
- Around 4:00am started having problems with the BigBite Magnet
- Techs recovered BigBite Magnet during morning
- Working on Beam Recovery
Recent Issues
- BigBite Magnet trips with overtemperature and overvoltage error, now resolved
Current Status
- Beam Recovery, then return to production
Run Plan
- Continue running 45 uA on He3
Data Collection and Polarization Status
- 39.7 C of uncorrected charge for this kinematic (44.9C of corrected charge which is 28% of the plan)
- Last NMR 51.5%
Other Topics/Status Updates
- Readiness target replacement
- Moller polarimeter readiness
- 7 Shifts still need filled during the remaining run period