RC meeting and Run Plan, Wednesday February 22th

From SBS wiki
Jump to: navigation, search

RC Report

Summary

  • Beam delivery is as usual
  • We had ~45 uA beam some times
  • Total charge collected over last three shifts is just 1.1C

Issues

  • Average beam current is on the level of 1/3 of projected 45 uA

Current Status

  • Production on He-3 target when beam is available

Run Plan

  • Continue running 45 uA on He3
  • Accelerator will prioritize beam and not have any maintenance days this week

Data Collection and Polarization Status

  • 38.9C of uncorrected charge for this kinematic (44.3C of corrected charge which is 28% of the plan)
  • Last NMR 48%

Other Topics/Status Updates

  • 7 Target Operator Shifts need to be taken
  • Readiness for Monday 3/27 target replacement?
  • Moller polarimeter readiness for 3/28 run?

Requested Accesses to the Hall

  • Holly need access related to SBS GEM electronics