RC Meeting Information

Run Coordinator: Arun Tadepalli

Time: 3:15 pm

Remote connection link: https://jlab-org.zoomgov.com/s/1619032184

Or join meeting with the following methods Phone one-tap Phone one-tap: US: +16692545252,,1619032184# or +16468287666,,1619032184# Join by Telephone For higher quality, dial a number based on your current location. Dial: US : +1 669 254 5252 or +1 646 828 7666 or +1 551 285 1373 or +1 669 216 1590 or 833 568 8864 (Toll Free) Meeting ID: 161 903 2184 International numbers Join from an H.323/SIP room system H.323: 161.199.138.10 (US West) 161.199.136.10 (US East) Meeting ID: 161 903 2184 Passcode: 260715 SIP: 1619032184@sip.zoomgov.com Passcode: 260715

RC Report

  • After inserting the sieve into place (https://logbooks.jlab.org/entry/3981120) during early swing shift, we were able to successfully complete our optics program for this kinematic setting. With MCCs escorted access help (https://logbooks.jlab.org/entry/3981263), the sieve was removed and we continued with production running on LH2 and LD2. We had a rather smooth night of data taking during the owl shift. Early this morning, we were told that Hall A would have a brief beam interruption (~1hr) due to 2 pass separator phase drift work. In the meantime, we experienced quite a few trips due to SBS magnet spiking (https://logbooks.jlab.org/entry/3981601, https://logbooks.jlab.org/entry/3981570, https://logbooks.jlab.org/entry/3981575) and the FSD readout trips limits were adjusted after David Flay spoke with MCC. Currently, we are continuing with our production running with 100M LD2 and 20M LH2 cycles and 2hr long runs (instead of 1hr) and an occasional dummy target run.

Upcoming Shifts Which Need To Be Filled

  • Monday, Feb 7th Owl SL

Accelerator and Hall Status

  • 2nd pass separator work at 9:00 AM (1 hr down time)

Run Plan


To do

  • BCM calibrations - Friday day shift (David Flay available for questions)

Resolved Issues

Unresolved Issues

Subsystem Updates

  • Beamline:
  • DAQ general
  • HCal
  • BBCal
    • Correct HV files were uploaded and BBCALDISC thresholds adjusted accordingly to get a manageable rate for the optics run.
    • All settings optimized for production running.
  • Timing Hodoscope
  • GRINCH
  • GEMS
    • Pedestal run taken during an opportunistic beam down time during which the sieve slit installation was also accomplished.
  • Replay analysis