RC meeting and Run Plan, Thursday December 8th

From SBS wiki
Revision as of 10:08, 8 December 2022 by Ericking (Talk | contribs) (Created page with "Return to the RC Meeting Calendar = RC Meeting Information = * Current RC: Eric King <b>Time: Daily at 3:30pm</b> * Location: Counting house...")

(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to: navigation, search

Return to the RC Meeting Calendar

RC Meeting Information

  • Current RC: Eric King

Time: Daily at 3:30pm

  • Location: Counting house conference room

Shift Schedule

Accelerator Status

  • Everything appears to be running smoothly at the moment.
  • Hall C is down for about a week due to a vacuum break.

Current Status

  • The experiment was back up and running yesterday evening by 8PM. :)
    • Beam restoration went smoothly with a beam width of ~330 x ~320. [4098298]
    • Bill's carbon hole analysis looks fine. [4098365] [4098360]
  • Poor GEM track efficiency, alignment needed for analysis. Last spoke with Zeke at around 1:30AM'ish and he will continue working on alignment this morning after collaborating with other GEM experts. [4098462] [4098439] [4098413] [4090862]
  • Accelerator has agreed to support a Møller measurement during Friday DAY.
    • Accelerator last time didn't get started until about 9:30'ish. Target Operator still required. Shift leader should still come in as of now.

Issues Resolved

Issues remaining

  • BB GEM APV unreachable and cannot be repaired at this time.
  • Beam step size jump is still unresolved (I'm not clear if this has been resolved; I sent Jay an email asking for clarification for myself; Mark suggested that it would be nice if someone made, or has made, an ELOG record of this)

Short Term Run Plan

  • Continue production run on He3 target, 36 uA
  • Use GEnII-noSBSGEMs DAQ config
  • Use ps3=0, ps5=6, others =-1
  • BBCal threshold at -366 mV, HCal threshold at -19 mV
  • NMR measurement every 3 - 4 hours, close to 4 hours is better

Planned Accesses to the Hall

  • I presume that repairs for the BB GEM APV will wait until shutdown.

Special Requests

  • None of which I'm aware, please email me ericking (@jlab.org or @temple.edu) if there's something to be added.

Notices in Effect for Shift Crew

  • Power down SBS, BB, and Detector HV before making an access to the Hall

Data Collection Status

  • 74 out of 141 days (~52.5%)
  • Total uncorrected accumulated charge on He3: 47.020 C out of 232C (20.26%)
    • 2-Pass: 13.467 C
    • 3-Pass: 33.553 C (at end of OWL)