RC meeting and Run Plan, Wednesday April 23th
From SBS wiki
Contents
RC Meeting Information
RC: Jimmy Caylor
Useful Links
Notices in Effect for Shift Crew
- For controlled access call the RC and together you will fill out the Hall access checklist. [1]
- Please pay attention to BTM, incorrect accounting is happening. also make sure to submit all hours, including the last one.
- Please fill out the shift checklist and notify RC if there are any issues
Current Status
On the accelerator side:
- Hall C in the middle of switch to 4 pass
--> Wien angle to -39.2
- Beam studies on Thursday (delivery to Hall A dump)
On the Hall side:
- Some HCal voltage set points got set to zero
--> Now has an alarm if at 0 V even if setpoint is zero
- Detectors and DAQ seem to be working well (SBS GEMs in much better shape)
- Production running at 17 uA overnight maximized trigger rates
--> Could be pushing the front track too hard
--> Might need to back down with the current
- Production running until they make us stop
--> Wien change - how do we want to handle this?
Current Issues
- SBS GEM efficiency (optimize tracking efficiency vs current)
--> Update on work done during access
- Active analyzer peak search on-going?
- Communication loss overnight - https://logbooks.jlab.org/entry/4287266
Special Requests
Sub-systems
- SBS and BB magnets
- BB GEMs
- BB Grinch
- BB Cal - Production threshold changed to 1.4 Gev
- BB scin
- SBS GEMs - See logbook
- SBS analyzer + RP hodo - Channels 30 and 31 tripped during lumi scan for GEMs
- SBS HCAL - https://logbooks.jlab.org/entry/4287249
- DAQ
- Analysis
- Target
- Beam line
- Moller
- Raster