Summary
Yesterday (04/24) GEM Zero suppression threshold changed to 2 sigma as was agreed during the RC meeting (https://logbooks.jlab.org/entry/4288151). Bill Henry also changed the fadc window to 1500 ns as with the narrower window we were missing the peak (https://logbooks.jlab.org/entry/4288223).
We had a few DAQ issues overnight that were fixed by Alex. Other than that data taking was smooth overnight. We are currently running at 12 uA on LD2. Later today we might decide to go up to 15 uA.
MCC scheduled Hall A beam studies today, which will start at 8:30 am and continue throughout the Day shift.
Swing shift summary (https://logbooks.jlab.org/entry/4288152).
Owl shift summary (https://logbooks.jlab.org/entry/4288443).
We will have our daily 3:30 pm RC meeting on the 2nd floor of the counting house and on zoom.
Planned Access to the Hall
Jiwan wants to make a quick access to fix HCal hv.
Accelerator
MCC scheduled Hall A beam studies today, which will start at 8:30 am and continue throughout the Day shift.
Current Run Plan
We are currently running at 12 uA on LD2. Later today we might decide to go up to 15 uA.
During the RC meeting today we decided to do threshold studies (see https://logbooks.jlab.org/entry/4288910) to better understand efficiency.
See also Experiment run plans.
Current Issues
n/a
Future plans
MCC does not plan any major beam changes up until May 14th.