RC meeting and Run Plan, Tuesday May 14th

From SBS wiki
Jump to: navigation, search

Back to the calendar

RC Meeting Information

Current RC: Holly Szumila

RC Daily Meetings are at 3:30 (pm) via Zoom and in person in the counting house meeting room (2nd floor)

Useful Links

Summary

Planned Access to the Hall

Accelerator

Plan unchanged from yesterday:

  • no Wien angle change Tuesday for Hall A pass change;
  • Accelerator beam studies currently scheduled on May 19th starting at 7am
  • Pass change for Hall C Wednesday day shift

Current Run Plan

  • Raster is on.
  • Target is LD2 with a radiator
  • Set BB magnet on (750 A).
  • Ask MCC to turn SBS magnet on at 2100 A (100 %).
  • Load BBCal HV settings for BB on, SBS-100 %.
  • Set ps3 to 0, all others to -1 (coin trigger).
  • Set BBCal threshold to approximately ?? GeV ( ?? mV) for (scan) BBCALHI and (leave as-is) BBCALLO, nominal HCAL threshold.
  • Starting at 1 μA, observe rates on HCal and BBCal.
  • GEM expert present: turn on GEMs at reduced HV (3600V). Begin to check rates and compare to GEn-RP running. Increase beam current and HV as able.
  • Maximum 5uA on deuterium+radiator pending daq rates.
  • Take data at established beam current for remainder of the experiment.
  • Moller measurement--when??

Current Issues

Future plans

Neutron detection efficiency measurement feasibility