RC Meeting Information

RC: Jimmy Caylor

Useful Links

Notices in Effect for Shift Crew

  • For controlled access call the RC and together you will fill out the Hall access checklist. [1]
  • Please pay attention to BTM, incorrect accounting is happening. also make sure to submit all hours, including the last one.
  • Please fill out the shift checklist and notify RC if there are any issues


Current Status

On the accelerator side

  • Physics beam delivery around 3 am in owl
  • Beam studies on Thursday (delivery to Hall A dump)

On the Hall side

  • Quick beam checkout with carbon hole - beam position fine
  • GEM test with hardware thresholds 3, 2, 1 sigma.
    • Data rate increased by 30% at 2 sigma
    • Data rate increased by 300% at 1 sigma
  • Data rate at 12 uA right now is 400 MB/s
  • GEM work while the hall was open was able to get rid of some holes in both BB and SBS GEMs
    • roughly 70% efficiency per layer in the rear tracker at 8 uA LH2
    • David and Bill were able to find an peak in the active analyzer with some analysis cuts


GEN-RP KLL run plans

Current Issues

  • SBS GEM efficiency (optimize tracking efficiency vs current)

Special Requests

Sub-system