RC meeting and Run Plan, Wednesday April 18th

From SBS wiki
Revision as of 13:25, 18 April 2024 by Simona (Talk | contribs) (Sub-systems)

(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to: navigation, search

<< Back to Daily Meetings

RC Meeting Information

RC: Jimmy Caylor

Useful Links

Current Status

On the accelerator side:

--> Beam was delivered into the hall overnight.

--> Raster size was far too large (like 10x10 mm) for the requested 3x3 mm. This caused significant confusion overnight.

On the Hall side:

--> Started beam check out late swing/owl but were confused by raster.

--> Raster size could not be verified so Moller measurement was started.

--> Concluded that raster was very large and using the carbon hole empirically set the size of the raster.

--> Beam check out was completed and detector check out is ongoing.

Current Run Plan

GEN-RP KLL run plans

Notices in Effect for Shift Crew

  • For controlled access call the RC and together you will fill out the Hall access checklist. [1]

Current Issues

  • Some GEM crate issues

Planned Accesses to the Hall

  • Steel analyzer insertion in the morning. Shielding bricks? HCal timing change?

Special Requests

Sub-systems