RC meeting and Run Plan, Friday February 4th

From SBS wiki
Jump to: navigation, search

<<SBS Main<<Run Coordinators <<Daily Meetings

RC Meeting Information

Run Coordinator: Arun Tadepalli

Time: 3:15 pm

Remote connection link: https://jlab-org.zoomgov.com/j/1619032184?pwd=aWhTVWxya1ZZQzA1K2ZPSTd2ZXZ2QT09#success

Or join meeting with the following methods Phone one-tap Phone one-tap: US: +16692545252,,1619032184# or +16468287666,,1619032184# Join by Telephone For higher quality, dial a number based on your current location. Dial: US : +1 669 254 5252 or +1 646 828 7666 or +1 551 285 1373 or +1 669 216 1590 or 833 568 8864 (Toll Free) Meeting ID: 161 903 2184 International numbers Join from an H.323/SIP room system H.323: 161.199.138.10 (US West) 161.199.136.10 (US East) Meeting ID: 161 903 2184 Passcode: 260715 SIP: 1619032184@sip.zoomgov.com Passcode: 260715

RC Report

  • We resumed production running during swing shift until beam was taken away from us due to vacuum problems during the owl shift. Apparently they are finished with the repair work and will take about four hours to restore beam. We should expect beam during early swing shift (https://logbooks.jlab.org/entry/3982134) and will continue to take cosmics to keep the pot boiling.


Upcoming Shifts Which Need To Be Filled

  • Monday, Feb 7th Owl SL

Accelerator and Hall Status

Run Plan

To do

Resolved Issues

Unresolved Issues

Subsystem Updates

  • Beamline
  • DAQ general
    • Fixed problems with APV.
  • HCal
    • Software organization
    • 50k plots looks good
  • BBCal
    • Taking cosmic runs at -40 mV BBCAL threshold. Will restore to production settings after beam returns.
  • Timing Hodoscope
    • Rachel M looked at TH plots and all looks ok.
  • GRINCH
  • GEMS
    • Nothing new to report besides APV problems.
  • Replay analysis
    • We could push to 12 uA for LD2 but stay at the same current for LH2 (15 uA)